PURPOSE: The primary objective of this project is to deliver HP gas from the Fort Mill Lateral to the Springfield Station via a new 5.9-mile, 8-inch pipeline, which in turn will add more capacity to Fort Mill and the northern area of York County. Upon the conclusion of this project, the new pipeline and the additional supply of gas at Springfield Station will also help to alleviate the demand at a handful of meterinf & regulation stations intended to flow gas towards Tega Cay and the west side of Fort Mill.
LOCATION:The Fort Mill area of York County, adjacent to Fort Mill Parkway & Springfield Parkway
TIMELINE: Fall 2022 – Summer, 2020
CONTRACTORS INVOLVED:
Environmental Consulting/ Permitting – S&ME, Inc.
Land Clearing & Erosion Control – T&L Farms
Pipeline Contractor – G. Campbell Construction
Survey – The Thrasher Group North Carolina, Inc.
3rd Party Inspection – National Inspection Services
X-Ray – Vantage Point Inspection
PROCESS:
Surveying
Design & Plan Preparation
Environmental Permitting
SCDOT Encroachment Applications
Clearing
Construction
Hydrostatic Pressure Test
Final Tie-ins and purge to gas
Stabilization
STATUS: Project to be substantially completed, Summer 2024